Belle Glade > Project Tasks  

Project Tasks

Modify settings and columns
Use the Tasks list to keep track of work that you or your team needs to complete.
Project Tasks
  
View: 
Sort by AttachmentsUse SHIFT+ENTER to open the menu (new window).
1. 10-03-2008 Location Evaluation Use SHIFT+ENTER to open the menu (new window).
Brent AndersonCompleted(2) Normal10/3/2008
100%
2. 03-25-2009 Survey ReportUse SHIFT+ENTER to open the menu (new window).
Brent AndersonCompleted(2) Normal3/25/2009
100%
3. Conceptual Design (30%)Use SHIFT+ENTER to open the menu (new window).
Brent AndersonCompleted(2) Normal8/15/2009
100%
4. ERP PermitUse SHIFT+ENTER to open the menu (new window).
Brent AndersonIn Progress(2) Normal8/31/2010
50%
5. Preliminary Design (60%)Use SHIFT+ENTER to open the menu (new window).
Brent AndersonCompleted(2) Normal3/17/2010
100%
6. Detail Design (100%)Use SHIFT+ENTER to open the menu (new window).
Brent AndersonIn Progress(2) Normal8/31/2010
7. Bid Package/Bid Results EvaluationUse SHIFT+ENTER to open the menu (new window).
Brent AndersonNot Started(2) Normal
8. Construction Inspection Month 01Use SHIFT+ENTER to open the menu (new window).
Brent AndersonNot Started(2) Normal